What is the resource leveling?

In project management, resource levelling is defined by A Guide to the Project Management Body of Knowledge (PMBOK Guide) as "A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply."

Accordingly, what is crashing and fast tracking?

In summary, the differences between fast tracking and crashing are: Fast tracking involves the performance of activities in parallel, whereas crashing involves the addition of resources to a project. In fast tracking, there is increased risk, whereas in crashing there is increased cost.

What is schedule compression technique?

Schedule compression is a technique used in project management to shorten an already developed schedule. This might be done to meet an update delivery date, a new opportunity or schedule delay. It's done without changing the scope of the program. There are two techniques that are commonly used in schedule compression.
Write Your Answer

Rate

80% people found this answer useful, click to cast your vote.

4 / 5 based on 1 vote.

Bookmark

Press Ctrl + D to add this site to your favorites!

Share